CPUC General Order 143-B is the California Public Utilities Commission's safety rule for light rail transit. Its section 14.05 requires every light rail system to run a track maintenance and inspection program, uses FRA's Part 213 as a guideline, and requires track inspection records for the four prior calendar years. General Orders 164-F and 175-A add safety plan oversight and roadway worker protection.
None of the three orders sets an interval for internal rail testing, and none names ultrasonic testing. On California light rail, the rail test interval comes from the agency's own safety plan and track standards, which the CPUC reviews.
This page covers the California layer only. For the national map of regulators, see our guide to railway safety standards.
Who oversees light rail safety in California?
The California Public Utilities Commission (CPUC) is the state safety oversight agency for rail transit in California, and its Rail Transit Safety Branch does the field work. The CPUC's authority comes from 49 U.S.C. 5329, 49 CFR Part 674 and sections 778 and 99152 of the California Public Utilities Code, as General Order 164-F section 1.1 states.
The CPUC's list of regulated rail transit agencies, read on November 16, 2026, names 15 agencies and systems. They range from large light rail and rapid transit operators to airport people movers and two shopping-center trolleys, and two are listed as under construction.
General Order 164-F defines what falls inside that oversight. Section 2.26 covers any light, heavy or rapid rail system, monorail, inclined plane, funicular, trolley, cable car, automatic people mover or automated guideway transit system used for public transit, "or any such system in engineering or construction", that is not regulated by the Federal Railroad Administration.
The CPUC's rail transit rules page lists five General Orders written for transit.
| General Order | Subject | Version on the CPUC page, November 2026 |
|---|---|---|
| GO 127 | Automatic train control on rapid transit systems | Adopted August 15, 1967 |
| GO 143-B | Safety rules and regulations governing light-rail transit | Adopted May 8, 1991; last amended January 20, 2000 (Resolution ST-47) |
| GO 164-F | State safety oversight of rail and other fixed guideway systems | Adopted and effective January 16, 2025 (Resolution ST-259) |
| GO 172 | Personal electronic devices used by rail transit employees | Adopted October 6, 2011 |
| GO 175-A | Roadway worker protection by rail transit agencies | Adopted March 17 and April 12, 2016 |
Key takeaway: on California rail transit outside FRA's reach, the CPUC writes the safety rules, reviews the agency's safety plan and inspects the property.
What does CPUC General Order 143-B require for light rail track?
CPUC General Order 143-B requires each light rail system to establish a track maintenance and inspection program and to keep track inspection records for four prior calendar years; it treats FRA's track standards as a guideline, not as adopted law. The order covers light rail design, construction, operation and maintenance, and applies to public transit guideways "planned, acquired, or constructed on or after January 1, 1979" (section 1.04).
| Section | What it says | Why it matters for inspection |
|---|---|---|
| 9.01 Track requirements | The American Railway Engineering Association (now AREMA) Manual for Railway Engineering "shall be used as a guideline" for track design and construction; alternatives are noted on plans filed with the CPUC | Rail section, weld and fastening choices trace to the agency's design criteria, not to a state table |
| 14.01 and 14.02 | CPUC representatives may enter the property to check compliance, make tests and inspect records, and the system must give them reasonable opportunity to do so | Test records may be read by a state inspector, not only by the agency |
| 14.05 Track maintenance practices and records | A track maintenance and inspection program is mandatory; Part 213 sections are the guideline; records are kept four prior calendar years | The core track clause, quoted below |
| 1.07 Exemptions | A request must show "that safety is not reduced" and is limited to the particular case | An agency can't quietly drop a requirement; it files for relief |
The central sentence of section 14.05 reads:
"The Federal Railroad Administration (FRA) track safety standards contained in Section 213.9 of sub-part A and all of sub-parts B, C, D, and E as published by the FRA in Title 49, Chapter II, Part 213 of the Code of Federal Regulations shall be used as a guideline to establish minimum safety standards and inspection intervals." — CPUC General Order 143-B, section 14.05
Where an agency's alternative standards and inspection intervals are less stringent than those in Title 49, "they shall be filed with the Commission". Records of periodic track inspections, "showing defects and deviations from the adopted standards along with the corrective action taken", are kept on file for the four prior calendar years.
Table 1 of GO 143-B ties maximum speed to the alignment class and the train protection system.
| Alignment (section 9.04) | Train protection | Maximum permitted speed (Table 1) |
|---|---|---|
| Exclusive right-of-way | Automatic train protection and automatic train stop | No limit set by the order |
| Exclusive right-of-way | Automatic block signals only | 55 mph |
| Exclusive right-of-way | None required | 45 mph |
| Street median or side alignment with a 6-inch curb, traffic signal at crossings | None required | Legal speed of parallel traffic, not above 35 mph |
| Mixed traffic on surface streets | None required | Legal speed of parallel traffic, not above 35 mph |
| Pedestrian mall | None required | 20 mph |
Key takeaway: GO 143-B makes a track inspection program and four years of records mandatory, and leaves the numbers to the agency's adopted standard, with Part 213 as the yardstick.
Does General Order 143-B set a rail testing interval?
General Order 143-B does not set an internal rail testing interval, because the Part 213 subpart that holds the rail test rule is not in its list. Section 14.05 names section 213.9 and Subparts B, C, D and E. Part 213's inspection sections, including 213.237 on internal rail inspection, sit in Subpart F.
| Part 213 material | Subject | Named in GO 143-B 14.05? |
|---|---|---|
| Section 213.9 (Subpart A) | Track classes and maximum speeds | Named |
| Subpart B | Roadbed | Named |
| Subpart C | Track geometry | Named |
| Subpart D | Track structure, including 213.113 defective rails | Named |
| Subpart E | Track appliances and track-related devices | Named |
| Subpart F | Inspection: 213.233 visual, 213.237 internal rail, 213.238 qualified operators, 213.241 records | Not named |
A text search of the three General Orders supports the reading. The words "ultrasonic", "rail flaw", "internal defect" and "nondestructive" appear nowhere in GO 143-B, GO 164-F or GO 175-A as posted by the CPUC in November 2026.
Section 14.05 asks for "inspection intervals" but points to subparts that hold limits, not frequencies. In practice the interval for ultrasonic rail testing on a California light rail line is whatever the agency writes into its own track standards and safety plan.
Two outside references often supply the number. FRA's 49 CFR 213.237 uses 370 days or 30 million gross tons, whichever is shorter, for Class 4 and 5 track and for Class 3 track with scheduled passenger trains. APTA's voluntary standard RT-FS-S-002-02 Rev. 1 (2017) calls for ultrasonic rail flaw detection of mainline track at least once a year. Neither binds a California light rail agency until the agency adopts it.
Subpart D is in the list, though, and that matters once a defect is found. The remedial action table in 213.113 is part of the guideline, so an agency that follows GO 143-B's yardstick will treat a transverse defect or a bolt hole crack much as a railroad would. Our guide to FRA track safety standards explains it.
Key takeaway: GO 143-B borrows Part 213's limits and its defective rail rule as a guideline, but not its rail test interval; the agency's own document sets how often rail is tested.
What does General Order 164-F require of the agency's safety plan?
General Order 164-F requires every California rail transit agency to keep a Public Transportation Agency Safety Plan that describes, among 21 listed elements, how its facilities and equipment are inspected and tested. It is the CPUC's Part 674 program in rule form, and the current version took effect on January 16, 2025.
Section 3.2(n) is the inspection clause. The safety plan must describe the process used for facilities and equipment safety inspections, including four items.
| GO 164-F section 3.2(n) item | What a rail testing program supplies |
|---|---|
| (i) The facilities and equipment "subject to regular safety related inspection and testing" | The track segments, yards, turnouts and welds in the test scope |
| (ii) "Techniques used to conduct inspections and testing" | The method named in plain terms, such as ultrasonic rail flaw testing by cart, hi-rail or hand scanning |
| (iii) "Inspection schedules and procedures" | The interval the agency has adopted and the written procedure behind it |
| (iv) How results are entered in the hazard management process | The path from a defect report to a tracked hazard and a remedial action |
This is where the rail test interval becomes enforceable. Once an agency writes an interval into its plan or track standards, section 3.3 lets CPUC staff check whether actual practice matches it.
Several other clauses reach an outside testing firm directly.
| GO 164-F clause | Requirement | Effect on a contractor |
|---|---|---|
| 2.4 | A contractor is "an entity that performs tasks on behalf of FTA, Commission, or RTA through contract or other agreement" | Contractors are inside the rule's vocabulary |
| 3.2(p) | The plan describes training and certification for "employees and contractors" in safety-related positions, with a process to keep and access contractor training records | Expect to hand over qualification records |
| 3.2(r) | The plan describes the safety requirements contractors must follow on or near agency property | The agency's rules are a contract term |
| 3.2(u) | Safety principles and requirements are included in the procurement process | Safety terms appear in the solicitation itself |
| 3.3 | CPUC staff may inspect and review, with access to "all facilities, documents, and records" | Test reports may be requested by the state |
| 3.4 | On-site CPUC review of the plan at least once every three years | Records from the last three years get read together |
| 5.1 and 5.2 | Annual internal safety audits, covering every plan element within each 3-year period | The inspection program is audited by the agency too |
| 9.1 and 9.5 | Corrective action plans for findings from investigations, audits, hazards and CPUC inspections | A gap in testing or records becomes a tracked action |
GO 164-F also sets the reporting clock for serious events. Section 7.1 requires the agency to notify CPUC staff within two hours of an immediately reportable safety event, and section 7.2 lists a derailment among those events. An investigation corrective action plan is due within 60 calendar days of the event (section 9.2).
The CPUC backs the orders with a citation program. Resolution ST-163, adopted December 18, 2014, lets staff cite violations of the transit General Orders, with scheduled penalties from $2,000 to $10,000 per incident and, for some items, $250 a day.
Key takeaway: GO 164-F doesn't tell an agency how often to test rail; it makes the agency write the answer down, follow it and show the records.
What does General Order 175-A require before anyone enters the track zone?
General Order 175-A requires every California rail transit agency to protect roadway workers with written rules, a job safety briefing before any roadway work, and controls on train movement that depend on the kind of work. It applies to anyone doing work on the right-of-way, and its definition of "employee" includes "a contractor working on behalf of such RTA" (section 2.3).
| GO 175-A section | Rule | What it means for a rail test |
|---|---|---|
| 2.22 | The track zone is the area "within six (6) feet of the outside rail on both sides of any track" | A walking stick or cart test is always inside the zone |
| 2.5 | The 15-second rule: be clear or in a place of safety 15 seconds before a vehicle at maximum authorizable speed could arrive | Sight distance sets where a lookout-based method is even possible |
| 2.10 | On-track equipment is any rolling equipment besides revenue vehicles, "including but not limited to testing, inspection, and maintenance" | A hi-rail test truck or test cart is on-track equipment |
| 3.10 | Anyone allowed into the track zone "shall either complete the required RWP training or be escorted by an RWP-trained employee" | Training or an escort is settled before mobilization |
| 5.1 | The employee in charge gives a job safety briefing before any roadway work | No briefing, no access |
| 6.3 | Work with tools, machines or equipment needs an authorized work area, confirmed communication with the control center and one of five movement controls | Rail testing is section 6.3 work, not a "minor task" |
Section 6.3 governs testing. Its five controls are flags with a watchperson, an approved no-flag method with an early warning device, lining and locking switches or otherwise physically preventing entry, working with propulsion power down and barriers placed, or control-center stop commands on systems with positive train control.
Within working limits, section 6.3(e) allows rail transit vehicles, on-track equipment included, to move only under the direction of the employee in charge. They must move at a speed that allows stopping within half the range of vision, "and no greater than 25 miles per hour unless the EIC sets a slower speed".
Training has its own clock. Section 9.4(a) requires each agency to retrain roadway workers on its roadway worker protection program at least once every 24 months, and section 9.4(b) requires the training records to be kept at least three years.
Under section 6.3(g), a phone camera may be used in the track zone only if it is an agency-issued device made incapable of sending and receiving communications while there. GO 172, the personal electronic device order, defines "employee" to include contractors as well, and its section 3.1 prohibits using such devices while "performing any task while fouling the tracks".
Key takeaway: under GO 175-A a rail test is planned around the agency's protection method first; production rate comes second.
How do the General Orders connect to FTA Parts 671, 673 and 674?
The General Orders are California's way of carrying out three federal transit rules: Part 674 creates the state oversight role, Part 673 requires the agency safety plan, and Part 671 sets minimum roadway worker protection. None of the federal parts sets a rail testing interval either.
| Federal rule | What it requires | California counterpart |
|---|---|---|
| 49 CFR Part 674, State Safety Oversight | An independent state agency with investigative, inspection and enforcement authority that audits each agency's safety plan at least once every three years (674.13(a)) | GO 164-F, with the CPUC as the agency |
| 49 CFR Part 673, Public Transportation Agency Safety Plans | Each agency keeps a safety plan built on Safety Management Systems | GO 164-F section 3 lists what the plan must contain |
| 49 CFR Part 671, Rail Transit Roadway Worker Protection | A state-approved RWP program and a dedicated RWP manual (671.11, 671.13) | GO 175-A, which predates Part 671 |
Part 671 is the newest piece. Under 671.25, the state agency was to coordinate with each transit agency so that the RWP program was established and approved within one calendar year from December 2, 2024.
GO 175-A and Part 671 now apply together, and the wording differs in places. GO 175-A fixes the track zone at six feet from the outside rail, while Part 671 defines it as the area the agency identifies "where a person or equipment could be struck by the widest equipment that could occupy the track". Both use the same 15-second measure, and both require refresher training at least every two years.
GO 175-A's own authority clause still cites 49 U.S.C. 5330 and 49 CFR Part 659, which have since been repealed and rescinded. Ask the agency which RWP manual revision the CPUC has approved.
Key takeaway: federal rules create the plan, the oversight and the worker protection floor; the General Orders add California detail on top.
When does FRA regulate a California light rail line instead?
FRA regulates a light rail operation where it runs on, or connects to, the general railroad system; the CPUC regulates the rest. FRA's track rule excludes track "used exclusively for rapid transit operations in an urban area that are not connected to the general railroad system of transportation" (49 CFR 213.3(b)(3)).
The General Orders mirror that boundary. GO 164-F's definition of a rail fixed guideway system leaves out any system regulated by FRA, and its section 7.5 tells an agency that shares track or right-of-way with the general system, and is subject to FRA accident notification rules, to report to FRA under FRA's requirements.
Commuter rail is the common point of confusion. FRA treats commuter railroads as part of the general system whether or not they connect to it, so California's commuter operators follow Part 213, including the 213.237 rail test interval, and not GO 143-B.
On a light rail line with a shared segment, the shared track follows Part 213 in full, Subpart F included, and the rest follows the agency's CPUC-reviewed standards. Our rail inspection guide for government and transit authorities covers shared-use scoping in a request for proposals.
Worked example: one rail test on a 12-mile light rail line
The example uses a made-up line to show how the three General Orders touch a single ultrasonic rail test.
Inputs. A 12-mile California light rail line shares no track with a railroad. Nine miles run on fenced exclusive right-of-way with automatic block signals, and three miles run in a street median behind a 6-inch curb, with traffic signals at crossings. The agency's track standards call for ultrasonic rail testing of mainline track once a year.
Step 1: who regulates. No shared track means 213.3(b)(3) excludes the line from Part 213 as law. The CPUC oversees it under GO 164-F, and GO 143-B applies as a light rail system.
Step 2: speed and track class. GO 143-B Table 1 caps the block-signaled exclusive segment at 55 mph and the median segment at 35 mph. Under the 213.9 guideline, passenger trains may run at up to 30 mph on Class 2 track and 60 mph on Class 3 track. Both segments exceed 30 mph, so both need track that meets at least the Class 3 limits in Subparts B through E.
Step 3: rail test interval. GO 143-B supplies none. The once-a-year interval binds because the agency adopted it, and the safety plan must show it under GO 164-F section 3.2(n).
Step 4: sight distance. If a watchperson is part of the protection, the 15-second rule sets the distance needed at maximum authorizable speed.
| Speed | Feet per second (mph × 5,280 ÷ 3,600) | Distance covered in 15 seconds |
|---|---|---|
| 25 mph | 36.67 | 550 ft |
| 35 mph | 51.33 | 770 ft |
| 45 mph | 66.00 | 990 ft |
| 55 mph | 80.67 | 1,210 ft |
On the 55 mph segment a worker needs to see a train 1,210 feet away, and farther still to allow time to move clear. Curves and cuts rarely give that much, so rail testing is usually planned under a section 6.3 control that stops or excludes trains.
Step 5: training. A test technician completed the agency's RWP course on February 3, 2026. Under the 24-month retraining rule in section 9.4(a), retraining is due by February 3, 2028.
Step 6: records. The test runs on March 10, 2027 and finds one defect, which is removed that month. GO 143-B section 14.05 requires the inspection record, the defect and the corrective action to be on file for the four prior calendar years. Read literally, the 2027 record must still be on file through December 31, 2031.
Result. One night's test is governed by an interval the agency chose, a GO 175-A protection method, a training date and a records clock of almost five years.
What should a rail testing contractor expect in a California scope of work?
A California transit scope of work for rail testing usually carries the General Orders into the contract as access, training, records and reporting terms. Each agency's documents control.
- A named standard for the interval and the acceptance action. The scope should say which agency standard sets test frequency and which remedial action table applies when a defect is found.
- RWP training or escort, stated up front. GO 175-A section 3.10 allows either. Ask for class dates before pricing mobilization.
- A protection method per segment. Ask which section 6.3 control the agency plans for each segment and shift.
- Equipment approval. A hi-rail truck or cart is on-track equipment under GO 175-A, and it moves only under the employee in charge inside working limits. Our explainer on the hi-rail vehicle covers the federal side of that equipment.
- Qualification records. GO 164-F section 3.2(p) has the agency track contractor training and certification. Expect to submit technician certifications and RWP training records.
- A report that can be audited. Records should show the track tested, any track not tested and why, each defect with its location, and the corrective action, so they satisfy GO 143-B section 14.05 for four calendar years.
- Defect notification rules. Results enter the agency's hazard management process, so the scope should say who is called, how fast, and who decides on a speed restriction.
- Device rules. GO 172 section 3.1 and GO 175-A section 6.3(g) restrict phones and other personal electronic devices in the track zone. Ask the agency in writing how it treats test instruments, tablets and cameras.
For how these terms change production rates on cart and manual tests, see ultrasonic rail testing for metro and light rail systems.
What the General Orders don't cover
A scope of work should fill each of these gaps in writing.
- No rail test interval and no method. None of the three orders names ultrasonic testing or any other internal inspection method, and none sets a frequency.
- No operator qualification rule. Nothing in the orders matches 49 CFR 213.238 on qualified operators of rail flaw detection equipment. Qualification rests on the agency's requirements and the testing firm's written practice.
- No rail test record format. Section 14.05 says what track inspection records must show in general terms. It doesn't list report fields the way 213.241 does.
- GO 143-B covers light rail only. Rapid transit and people movers fall under GO 164-F and the other orders, but not under GO 143-B's track clause.
- Old text. The GO 143-B posted by the CPUC was last amended in 2000 and still names the American Railway Engineering Association, AREMA's predecessor. Confirm the current revision of every order with the CPUC before citing it in a contract.
This page has limits of its own. It summarizes orders read on November 16, 2026, it is not legal advice, and it does not describe any one agency's track standards, which are the documents that actually set test frequency.
How EMA Industries applies this
EMA Industries provides ultrasonic rail flaw testing for transit agencies, short lines and industrial track owners, along with rail weld inspection, and its capabilities include hyrail ultrasonic rail flaw detection and manual rail scanning. The company is based in Southern California and mobilizes nationwide. On a California transit property, the first scoping questions are the ones on this page: which standard sets the interval, which GO 175-A control protects the crew, and what the records must show for a CPUC review. To scope rail testing on a California light rail or streetcar line, contact EMA Industries.
Frequently asked questions
Does CPUC General Order 143-B require ultrasonic rail testing?
GO 143-B requires a track maintenance and inspection program, but it doesn't name ultrasonic testing or set a rail test interval. Section 14.05 uses Part 213's section 213.9 and Subparts B through E as a guideline, and the internal rail inspection rule, 213.237, is in Subpart F. The interval comes from the agency's own standards and safety plan.
Which California rail systems does the CPUC oversee?
The CPUC oversees rail transit and other fixed guideway systems that FRA does not regulate: light rail, rapid transit, streetcars, cable cars, funiculars, automated people movers and similar systems. Its list named 15 agencies and systems in November 2026, including two under construction. Commuter and freight railroads stay under FRA.
How long must light rail track inspection records be kept in California?
GO 143-B section 14.05 requires records of periodic track inspections, with defects and corrective action, to be kept on file for the four prior calendar years. Roadway worker training records under GO 175-A section 9.4(b) are kept at least three years. An agency's own records policy can require longer.
Do rail testing contractors need CPUC roadway worker protection training?
The CPUC doesn't run the training; each rail transit agency adopts its own RWP training program under GO 175-A. Anyone allowed into the track zone must either complete that agency's training or be escorted by an RWP-trained employee (section 3.10). Roadway workers are retrained at least once every 24 months.
Does FRA's Part 213 apply to California light rail?
Part 213 applies as law only where a light rail line uses track in the general railroad system. Elsewhere it applies as a guideline through GO 143-B section 14.05, which borrows the track classes and Subparts B through E. An agency that uses less stringent standards must file them with the CPUC.
Sources
- General Order 143-B, Safety Rules and Regulations Governing Light-Rail Transit (amended January 20, 2000), California Public Utilities Commission
- General Order 164-F, Rules and Regulations Governing State Safety Oversight of Rail and Other Fixed Guideway Systems (January 16, 2025), California Public Utilities Commission
- General Order 175-A, Rules and Regulations Governing Roadway Worker Protection Provided by Rail Transit Agencies and Rail Fixed Guideway Systems (2016), California Public Utilities Commission
- General Order 172, personal electronic devices (October 6, 2011), California Public Utilities Commission
- Rail transit rules and regulations and rail transit agencies regulated by the CPUC, California Public Utilities Commission (read November 16, 2026)
- Resolution ST-163, rail transit citation program (December 18, 2014), California Public Utilities Commission
- 49 CFR 213.3, Application and 49 CFR 213.9, Classes of track: operating speed limits, eCFR (text read on the Cornell LII copy, November 16, 2026)
- 49 CFR Part 671, Rail Transit Roadway Worker Protection, eCFR (671.1, 671.3, 671.5, 671.11, 671.13, 671.21, 671.25 and 671.41 read on Cornell LII)
- 49 CFR Part 673, Public Transportation Agency Safety Plans and 49 CFR Part 674, State Safety Oversight, eCFR (674.7, 674.13, 674.25 and 674.27 read on Cornell LII)
- 49 CFR Part 209, Appendix A, FRA statement of agency policy on jurisdiction, Cornell LII
- APTA RT-FS-S-002-02 Rev. 1, Rail Transit Track Inspection and Maintenance (2017, voluntary), American Public Transportation Association